on 09-24-2008 2:08 PM
Hi experts,
Could be possible control the budget exceeded by whole project no by any WBS Elemet?...
Currently, we are setting in the customizing
Proyect Systems-> Costs->Budget-> Define Tolerance limits
"Project availability control: Tolerance limits" to WBS Elemets.
But We want to control the budget exceeded by whole project
Example
BUDGET
Projects x 100
WBS x1 60
WBS x2 40
I d like the budget exceeded appears when WBS x2 costed more than 100.
Tks in advance,
Nachos
Thanks.
But I Couldnt follow you...
Could you give any example and How to set it?
Tks. in advance,
Nacho
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Don't distribute the budgets from the top level WBS element to lower level WBS elements.
Then the availability control will check the project budget (top level WBS's budget) rather than lower level WBS elements.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.