Hi Gurus,
A contract to be created for Service in Value Basis for 1 year.
I want to release the PO's based on contracts for every month and do the Service entry sheet and Miro respectively for each month.
What are the T codes to be used for the above process?
Regards
Use ME21N only
U can use stadard frame work order for making the contract for the validity u want.
u can put the activities in service order month wise each for each month.
regards,
sujit