Hi All

My employee has joined in 01.12.1999, but in SPRO we have set the earliest recalculation date for time management as 18.03.2002. I have made infotype 0003 empty. I am trying to delimit attendance quota from18.03.2002. to 31.08.2008

But I am getting a error message saying. Earliest retroactive accounting date time not possible

please suggest ASAP

Thanks

Veer

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

refer this

former_member682742
Participant
0 Kudos

Please check table T569 R 02.

Thanks,

Gajanan

Former Member
0 Kudos

Hi,

We have checked that table and in that table they have maintained 18.03.2002, but it's not allowing to delimit the Attendance Quota.

Thanks,

Veer