on 09-24-2008 11:32 AM
HI guru:
When I am going to create a Production order with HALB material, system is giving message "No suitable BOM alternative could be determined" while we have already created BOM, Routing for this material.
Please suggest what i am missing.
Thanks.
Virendra
ok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra,
Go to Your Production order and in Master Data tab.
Check which production version is selected.Then pick that production version and check its consistency in C223.Consistency result should be green signal along with valid BOM and Routing.
If there is any error is there then correct it.
Some of the reasons are,
- Valid From and To dates are not match
- Lot sizing limit of BOM doesn't match with Order qty.
- In active status of BOM
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check:
- BOM usage
- BOM's validity date
- order quantity
http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d2a9c44af11d182b40000e829fbfe/frameset.htm
http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d2aea44af11d182b40000e829fbfe/frameset.htm
Are you using several BOM alternatives? Are you using production version?
Regards,
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.