HI Friends,
this is shekar here i'm facing a problem with import PO while creating a po i have given different vendor for conditions like CVD,CUSTOMS,ECESS AND HECESS AFTER CREATING A Ppur order ,when i'm doing MIRO for the customs vendor with planned deliveries system not picking the values of the above given conditions plz tell me the procedure.
regards
shekar
this is answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
CVD ,ECESS,SECESS these all values u need to key in at the time of the MIRO.
This is the standard SAP practise of Import Scenario.
Reason to enter it manualy is -
1)U havent done GR earlier.
2)Exchange rate keep on changing so u cant use the PO values also .
Regards,
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai,
1.In general, you have to pay the Customs & CVD duties to the customs vendor before receiving th material in Import purchase.
2.Assign the Customs vendor to the Conditions in the PO - item level - conditions - condition types.
3.Remove the GR based IV in the Vendor master record of the customs vendor - purchasing data.
4.While doing MIRO wrt PO, select the planned delivery cost in the indicator tab.Enter the Currency INR in the Header data - Basic data. Here enter manually the values & Qty in the MIRO at the item level.You have to feed manually this data's in MIRO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.