on 09-24-2008 10:00 AM
Hi Experts,
I am using Assembly Processing for creating Projects through Sales Order.
when i am creating sales order, It asks for Std .network & std WBS..but further when saving it gives following error.
Is there a field where i can enter commitment item.
No commitment item entered in item 00010 P110
Message no. FI311
Diagnosis
The posted document contains at least one company code in which Funds Management, Cash Budget Management, or Project Cash Management is active. Therefore you must enter a commitment item in all involved company codes.
Procedure
Enter a commitment item.
If you cannot enter a commitment item, check with your system administrator that your account assignment derivation is adjusted so that the system can automatically derive a commitment item from another account assignment, or from the G/L or cost element.
Your project cash management configuration seems incomplete.
You get such error if you haven't created a commitment item for the GL account being used.
Use T Code FIPOS mention the company code, GL account execute, select the GL account that now appears in the GL account/commitment item assignment screen and click on fill and then save.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.