at are the activities carried out while releasing the production order?
Hi,
Order Release
Use
A production order must be released, before it can be processed. You can use the time period between creating and releasing a production order, for example, to carry out company checks and preparations. If you do not require this time period, you can automatically release the production order when it is created (see Automatic Release).
A newly created production order initially receives the status CRTD (created). The following restrictions apply to a production order that has been created:
Confirmations for the order cannot yet be executed.
Shop floor papers cannot be printed.
Goods movements for the order cannot yet be executed.
Releasing the order lifts these restrictions.
Features
Order release can be executed at the following levels:
With Release at Order Header Level all operations are released. The order and the operations receive the status REL (released).
With Release of an Operation the operation receives the status REL and the order receives the status PREL (partially released). If all operations in an order have been released, the order has the status REL.
Hope this helps.
Revert if you need more information.
Regards,
Tejas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Best way you should go through the SAP help library. You will get best explation there.
1) Material availability.
2) Cost calculation.
3)Capacity check.
4) PRT chcek as per OPJK.
5) Upadate missing part.
6)Printing of shope floore paper.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
While releasing the prduction order following activities are taken place:
1. Material availability check
2. Capacity availability check
3. PRT availability check
4. Printing shop floor papers
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
When u release production order following activities are carried out
1) Material availability.
2) Cost calculation.
3)Capacity check.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.