How can we carry MRP execution process for several plants under same company codes?
Define Scope of Planning and assign all plants that you want to include in MRP to the Scope of Planning
Regards,
Nilam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Defining Scope of planning, it is possible to run MRP for several plants.
To create scope of planning use tcode OM0E.
Insert all the plants which you want to run MRP.
Run MRP by tcode MD01.
In that screen make tick mark in define parellel processing.
In SPRO give server name in parellel processing.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.