Resource related billing

Hi experts,

One question is in my mind. Is it really required to do the resource related billing using DIP profile in PS or SD?

As per my understanding, if we are using DIP profile then only easy cost planning option has to be used for planning the cost of resources

Why cant we use automatic/network costing and by using milestone billing, a resource related billing is generated?

Thanks

replied

Hi Raghu,

The DIP profile defines and controls resource-related quotation and billing for SO and Sales documents. It may be maintained in either the CS or SD. The DIP profile allows flexible determination and translation of actual labor, material, and other costs into sales materials for appropriate pricing and billing.

where as Milestones are used in a project to designate significant events or start/completion of a project phase. Milestone usage is defined to trigger billing on the attached sales documents.

I hope it is cleared now.