target cost and actual cost

Former Member
0 Kudos

can any body explain diffrence between planned,target and actual cost

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

The actual cost is the Cost of the material after the Production Confirmation.

Plan cost is the cost of material before the production...

Target that means for this particular material the cost will be targeted eg:20 $ the after the production the cost of material should not exceed this cost. Genarally in CO we will define Target cost is getting calculated in the Production order based on the "Standard Cost Estimate" after GR. Planned costs are calculated based on the current costs.

The T.code KKBC_ORD for the Planned Vs Actual Cost is helpful report

In short:

Plan Cost = Planned Quantity X Planned Price

Actual Cost = Actual Quantity X Actual Price

Target Cost = Actual Quantity X Planned Price

Regards,

R.Brahmankar