Reorder point in project

Former Member
0 Kudos

Hi Friends,

We are doing projects. all our electrical items are stock items having mrp type VB and lotsize FX and mechanical items are having mrp type PD and lot size EX. Our BOM is having both mechanical and electrical items. So while transferring the material ,

1. what we have to select reservation for network, wbs or from plant stock.

2.all our plantstock , firmed reciepts to be considered.

3.what strategy group i have to select for the BOM 1st level item

Please suggest in detail....

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

As from MM point of view strategy type in MMR MRP 3 view is least used...

If you use ROP then strategy type need not be used..

If you use PD MRP i.e. material req plg. you could use strategy type MTS or MTO...

Reg,

Deepak.