Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Not all test transports have been imported

Hi All,

led me your eardrums for the SDMJ conundrum.

I have a maintenance project with the status "In Development with Release"

I have a change request that has the status "To be Tested"

When I select the action "Confirm Successful Test" I get 2 warnings.

1 - Status was reset by system

2 - Not all test transports have been imported

The details for #1 is

Status was reset by system Message no. SOCM_ACTION_LOG097 Diagnosis The required status value is not possible because of the data situation in SAP Change Manager. System Response The current user status has been reset by the system. Procedure The cause is displayed as a warning in the application log. Procedure for System Administration Analyze the situation in SAP Change Manager and rectify it.

#2 doesn't have any details.

I went to SE09 and all the tasks have been released. I went to my task plan and the transport of copies activity is green. Any ideas what's going on?

thanks,

Jason

Not what you were looking for? View more on this topic or Ask a question