Capacity Leveling MC29

Hi,

I just upgrade me SAP release from 4.7 to 6.0. Now i´m with some troubles on transaccion MC29 ¨Capacity Levelind¨.

On this transacción the black arrow that represent the time between notifications, start with the first notification and continue till the end of the planning fence !! This arrow always finish at tha planning fence, no mater which is the initial and ending time of the order or how many notifications i made !!

In 4.7, that works like i want, the black arrow goes from the first notification to the last one.

Any idea ?

Thanks in advance,

Dalmiro

Helpful Answer

by
Not what you were looking for? View more on this topic or Ask a question