suppose my production order has 200 ea quantity and 4 operations. when i confirm my 1st and 2nd and 3rd operation i am having 200 qty. but in between 3rd and 4th operation unexpected damage occored.and i lost 100.( let us think 100 are missing. this happens quiet often in seed industries).so to pack the product i need at 40 i need 200.

how do i do that.

this is a make to order scenario.

can i make it a rework order.

if i make it a rework order goods issue will not happen.

i think

then how do i do that.

in the same process if because of malfunctioning of machine wasted 100 uts of the material at operation 3 and i confirmed only partially for 100 items.but i need 200 uts to do my packing at operation 4.so even i in this case i have to issue good . how do i do that.