on 09-23-2008 7:25 PM
Hi!
What is the difference between an Implementation and Maintenance proejct in ChaRM?
For both of them I can create CR's. Is not?
Thank you very much much!
regards
Thom
Hi,
The main difference is that you can't create UC within ipmlementation project,
only regular corrections, test messages, and administration tasks.
Regards,
Oleg.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, Thom
I think the normal corrections in both cases are the same,
and the project workflow's look's similar.
from Sap Library:
[Workflow for Maintenance Cycles|http://help.sap.com/saphelp_sm40/helpdata/en/06/172e4208d06869e10000000a1550b0/frameset.htm] vs [Workflow for Implementation Projects|http://help.sap.com/saphelp_sm40/helpdata/en/1a/c39742042fc86ae10000000a155106/frameset.htm]
In my opinion, we use each project type for concrete task's (Implementation Project for business process implementation, Maintenance project - for solution maintenance).
Regards,
Oleg.