Availability check MD04

Hi all,

When I create a PO i've to enter the delivery date. If I put a week number the overview in MD04 says that the material will be available from the first day of the week (in my case Monday).

My questions are:

1. Is this possible to change?

2. What is the inpact on the rest of MRP?

Thanks in advance.

Maarten