on 09-23-2008 2:04 PM
Hi,
I have an issue with rescheduling horizon.
We have two plants maintained under same company code.
Rescheduling horizon maintained is 30days (in OPPQ) for both the plants with tolerance value 5days each (One difference is tolerance value forward for one plant is 0days).
But the MRP is considering only 23days for one plant and it works fine for the other plant (i.e., 30 days are considered for rescheduling horizon).
Could you please tell me, what other parameters are affecting the rescheduling horizon consideration by MRP?
Thanks and regards,
Nataraj
Edited by: Nataraj Shivamurthaiah on Sep 23, 2008 3:07 PM
Hi,
Check in material master have you assigned any MRP group. If so, use tcode OPPR, change rescheduling horizon to 30 days.
Now check the result.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dharma,
Thanks for your reply.
I have checked the MRP group(OPPR) assigned to the material.
For the plant which I am facing the issue the rescheduling horizon is maintained as 30days.
For the other plant (for which MRP results are fine) rescheduling horizon is not maintained in OPPR. So the MRP is considering the values maintained in OPPQ.
Could you please suggest me how the 23days were considered for the rescheduling horizon for one plant.
Thanks and regards,
Nataraj
Thanks for the support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.