on 09-23-2008 1:45 PM
HI EXPERTS
I HAVE A QUESTION TO MAKE....
I CAN'T UNDERSTAND THE MESSAGE IT COMES OUT WHEN I WANT TO GET AN OFFER (DEFAULT, ANYTIME WHATEVER ).
""Calculated processing end date is before the start date ""(HRBEN00FMODULES218)
WHICH INFOTYPE, PLACE, WAHTEVER HAVE I TO CORRECT?
PLEASE BE INFORMED THAT IN INFOTYPE 0171 I'VE ALREADY PUT AN ENTRY...
THANKS IN ADVANCE
Hi,
The employee in question would also need a valid record within IT 0378 - Adjustment Reasons.
Once this has been maintained, you will be able to proceed with enrolment via transaction code HRBEN0001
Hpe this will be helpfull