Dear All,
pl guide me that what is a schedule line in a P.R ?
what is it's importance ?
Regards & Thanx .
sap11
thsnx to all
sap11
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
We couldnt get directly Delivery Schedule of PR.For this we have to create Scheduling Agreement.It will be used as Source of supply in PR.
For this you should maintain
1.Source List (T_code ME01), for the material and assign the Scheduling Agreement here.
2. Specify the MRP Indicator as "1" or "2" as per requirement.
3. Go to MD02 and Run MRP, it will generate the Delivery Schedules and schedule lines.
Hope this will help you.
Regards,
Goraksh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Schedule line in PR gives the details of quantity and date on which the required material is to be delivered.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
U can set the schedule lines to be generated automatically during MRP via source list.
1.First create info record & scheduling agreement for a material.
2.Then create soucre list and assign tge scheduling agreement And assign the "source list usage MRP'' =2 (Record relevant to MRP. Sched. lines generated automatically) at ME01.
3. Set Schedule lines indicator in the initial screen of the planning run
Based on the demand system will create delivery schedules for a material.
regards
ram
Edited by: Parasuram M on Sep 23, 2008 4:55 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.