cancel
Showing results for 
Search instead for 
Did you mean: 

MD07: MRP Controller

Former Member
0 Kudos

Hi,

we have the following issue.

In T.Code MD07, we are giving the plant and MRP controller as Input. After that, once we enter into the screen, there is a button for define traffic light. Once we click on this, we will get a subscreen for traffic light. In this, traffic lights are the same for all the MRP controllers ( MRP controller should be vary in the selection criteria). Per the requirement, Business wants the traffic light selection criteria should be based on MRP controller.

For ex : if I select MRP Controler as 1, there should be some different traffic light criteria, If I select MRP Controller as 2, there shd be different traffic lights. Business wants to know whether this is possible or not?

Please let us know if any one have any idea on this? Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Any Idea on this issue?

Please suggest....