hi
you can map the process by creating two STO if bothe plants are under same company code.
First create the STO for the Raw materials form to receiving plant for Supplying plant
Then do the whole STO process by OBD, PGI and MIGO
Secondly once the FG or Semi finished are got ready then create another STO to map the Business scenario.
It will solve your purpose
Regards
Sujoy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
As per my view.
First create plant as vendor with XK01.
Then create Subcontracting purchase order for supplying and receiving plant with ME21N.
Here enter plant code in the field of vendor code.
also put roh material in material component in Material data available item detail level of purchase order.
Then create MIGO and MIRO.
Regards,
Mahesh Wagh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
http://www.sap-img.com/materials/sub-contracting-cycle.htm
Go through the link...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.