work center

Hello Experts,

It possible to have 'scheduling' tab view in workcenter without 'capacity' tab view?

In that case what is the use of the scheduling view.?

we have a WC catagory, in which the scheduling view is present and there is no capacity view.

In the scheduling view, the field 'capacity catagory' is mandatory.

so, an error occurs (since the capacity catogory is not maintained in capacity view..)

how to make that field as not mandatory.

Thanks in advance...

regards,

Ranjit

Former Member
Former Member replied

Hi Ranjit,

The tabs which are visible are because of work center catagory . Try changing work center catagory and see some tabs will not be visible .

Configuration in op40 and opfa .

Neal

Edited by: Neal Gibson on Sep 23, 2008 3:55 PM

0 View this answer in context