on 09-23-2008 10:04 AM
Hi SAP Gurus,
Sub contracting PO created on 2004 for Material 'x'. The component also same as the header material. ( Issuing component and recceiving component both are same ).
I have deleted the PO before issuing components to Vendor ( before 541 Mvt.)
But in MD04 the system driving sub contracting requirements against the deleted PO.
Is there any std correction program available to fix teh Issue.
Regards
Senthil.
Yes, there is correct progam, i have faced teh same problem
Check this OSS Note 128061 - Subcontracting: Inconsistencies in dependent requirements
Bhima