on 09-23-2008 9:33 AM
Can any body tell mw where to set the material is to be back flush in Material masters?? In Which view of the material?
Regards
Hi,
In MRP 2 view of Material master enter Backflush as 1 i.e. Always Backflush under "Procurement" Subscreen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
To determine whether a material is to be backflushed, you can make settings in the:
Material master record (MRP view)
Resource (Basic Data screen)
Master recipe (General Data screen for component assignment)
Process order (General Data screen for the material component)
Maintain the indicator for backflushing:
In the material master record, if you always want to backflush the material
In the master recipe or process order, if you only want to backflush the material from time to time
hope it helps..
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.