Backflushing indicator in Material Masters

Former Member
0 Kudos

Can any body tell mw where to set the material is to be back flush in Material masters?? In Which view of the material?

Regards

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

In MRP 2 view of Material master enter Backflush as 1 i.e. Always Backflush under "Procurement" Subscreen.

Former Member
0 Kudos

Any specific sub screen ?? because i am not able to view the option you suggested in material masters.

Regards

pankaj_singh9
Active Contributor
0 Kudos

"Procurement" Subscreen.

Answers (1)

Answers (1)

former_member581212
Active Contributor
0 Kudos

hi,

To determine whether a material is to be backflushed, you can make settings in the:

Material master record (MRP view)

Resource (Basic Data screen)

Master recipe (General Data screen for component assignment)

Process order (General Data screen for the material component)

Maintain the indicator for backflushing:

In the material master record, if you always want to backflush the material

In the master recipe or process order, if you only want to backflush the material from time to time

hope it helps..

Regards

Priyanka.P

Former Member
0 Kudos

I am not getting the resources means? What do you mean that? any specific path can you mention?

Regards