Hi,

I'm doing a goods receipt with reference to an Inbound Delivery via MIGO-GR.

If I do this, it will not update the status of my IB, it wil still be A, open...

How do I close/complete the status of my Inbound Delivery in this case?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI,

Has the picking been completed for the concerned Inbound delivery. If not then confirm the Quantity against each line item by putting the respective Qty in Putaway column.( confirm the Qts for putaway)

Then save. This shall complete the ID.

Then do the GR

Please check the same

Regards,

Prasanna

Award if helpful