Planning time fence in Strategy 50

Hi Experts,

I am testing a scenario in Strategy 50. I have given demand in MD61 for the matl with strategy 50. When I run MRP the BOM is not exploding.

I find that Planning time fence is creating problem. But in SPRO there is no planning time fence maintained . Nor I have given in material master lavel.

Please let me know how to explode the BOM.

Regards,

Former Member