Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Rough Cut Capacity Planning

Hey all,

i wanted to configure Rough Cut Capacity Planning in such a way that

1. i could view capacities of workcenters given that the demand (load) of planned orders could be executed in a particular period.

I accomplished this partially, meaning i could find out the bottlenecks on the workcenters but this was only on single material level, if i wanted to run this check on multiple the system, supposedly, offers me the option of using the product group, my question is, where do i view these bottlenecks on capacity IF i want to run RCCP on Multiple products.

2. i wanted to find out exactly how much i can produce in a period, given that the external and internal procurement lead times are incorporated this is usually reffered to as Master Production Scheduling, as far as i know atleast.

kindly shed some light on these matters.

Regards,

Danish

PS. i've seen similar posts to this but none directly addressing these issues hence i felt the need to ask these questions seprately.

Former Member
Not what you were looking for? View more on this topic or Ask a question