Error while MIGO

Former Member
0 Kudos

Hello Together,

While creating or extending material master our planning dept used to put profit center as a DUMMY_PROFIT CENTER which is no more active.

But our buyer can able to create PO with material which has a dummy profit center as well as our account clear can also able to do Import MIRO but we are facing problem while doing MIGO.

Following error message we are getting,

"Account 694005 requires an assignment to CO object"

This erro can be resolved by removing the dummy profit center from the material master but we need to cancle 1st PO as well as cancel the MIRO which is a big work.

Can anybody give me the best solution .

Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Check it in OKB9, I hope you already assign co object for this cost element. Check the account assignment category, if it is a busienss area mandatory. Select the cost element and double click on details per business area.Remove the default profit center against your valuation area and try it.

Regards

Maruthi.

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear,

You should create cost element for GL 694005.

After create cost element you should assign it to OKB9.

Hope above will helpful.

GOPAN