Maintenance Plan scheduling - Just Clarify

IP10 - can be used for individual Maintenance Plan till the Scheduling period.

IP30 - can be used for all Maintenance Plans in the system and also this is not relevant to the scheduling period. This can be executed after the scheduling period is over.

Can any one can justify the meaning what I have understood.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

What you have understood is correct and with out scheduling IP10 if you run IP30 it will generate orders before gong to run deadline monitoring the maintenance plan should be scheduled.

regards

satish

Answers (3)

Answers (3)

former_member192718
Active Contributor
0 Kudos

Dear Manmadhan Kounder,

IP10 you have understood correctly.

IP30 is same as scheduling for no. of plans.

You asking about scheduling period and scheduling. I would like to tell you here, even if you don't mention scheduling period then also IP10 and IP30 is going to schedule your plan, but in this case it will generate only one plan and call date.

If you mention scheduling period then IP10 and IP30 is going to generate till that period and once period is over and you again schedule with any of these two T-codes it will generate one plan with call date.

Regards,

Kaushal Rai

Former Member
0 Kudos

HI

IP30 automatic deadline monitoring to schedule a maintenance plan again or for the first time.

You have entered a start date or an initial counter reading in the scheduling parameters for the maintenance plan, or you have already scheduled the maintenance plan once.

ip10 you can schedule only for one plan.

IP30 you can schedule more than one plan.

both are same in scheduling