PM - Maintenance Plan scheduling

Maintenance Plan scheduling - Just Clarify

IP10 - can be used for individual Maintenance Plan till the Scheduling period.

IP30 - can be used for all Maintenance Plans in the system and also this is not relevant to the scheduling period. This can be executed after the scheduling period is over.

Can any one can justify the meaning what I have understood.

replied

Hi,

What you have understood is correct and with out scheduling IP10 if you run IP30 it will generate orders before gong to run deadline monitoring the maintenance plan should be scheduled.

regards

satish