Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Planned Cost for Internal Actvity

Dear All,

I am not able to get plan cost of internal actvity., after adding work center...

it's giving me followning error in cost calculation...

"In the routing for this material, operation 0010 (and possibly sub-operation ) points to work center MD01 in plant 6001. However, no cost center has been assigned to this work center. (Activities are valuated using the activity prices in cost center accounting to calculate the planned costs for an operation.)"

I have maintained cost center in work center also assign actvity type for it in KP26.

Also, i am not getting Default tab while creating work center in CNR3.

Please, let me know the reson for this if possible.

Thanks and Regards,

Atul R. Rajmane

Not what you were looking for? View more on this topic or Ask a question