Routing Machine time is not considered in planned order

Former Member
0 Kudos

While taking Mrp Run , routing Machine time is not considered for semi finish goods planned order

Case

There are 4 processes to convert raw material to finish, defined 4 semi finished items and there routing with Machine Process time, following parameters are mention for each semi finish item

u2022 Routing has base quantity of 1 EA and machine time as 120 Min.

u2022 Schedule margin key = 000 i.e all the float values is zero

u2022 In-house processing time in material master is 1 day

All 4 item planned order start date and finished date is the same.

Pls. guide.

Prakash

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member184655
Active Contributor
0 Kudos

Dear Prakash,

While running MRP what MRP control parameters are you using?

Check whether are you using value 2 for scheduling i.e Lead time scheduling and while running next time

use planning type as 3 Delete and recreate Planning data.

After taking the MRP run,now check whether are you able to see the operation start & end times.

Check & revert back.

Regards

Mangalraj.S

Former Member
0 Kudos

what is ur expectation from the system? how it should behave?

Pravin

Former Member
0 Kudos

Hi

In MRP run select 2 (lead time schedulling) against the schedulling processing key then it will consider routing

I assume u have maintained capacity and schedulling view for the work center.

Edited by: BNR on Sep 22, 2008 4:21 PM

Former Member
0 Kudos

Hi,

I tried with option 2 - Lead Time Scheduling and Capacity Planning, still it is not working.

In work center -> Capacity View

Capacity Category : 001 u2013 Machine

Processing Formula : SAP006 - Prod.: Machine rqmts

Control CapacityReduction : Formula-Related (in all three combo)

In work center -> Scheduling View

Capacity Category : 001 u2013 Machine

Processing Formula : SAP002 - Prod.: Machine time

Above parameter are maintained, if something is missing pls. guide.

Prakash

Former Member
0 Kudos

Hi,

In tcode OPU5, define scheduling parameter for planned orders, select your plant, order type & production scheduler.

Check in detailed scheduling, make tick mark in Scheduling & Capacity requirements.

Now rerun MRP with delete & recreate mode. Check the results.

Regards,

Dharma

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Please check the capacity of work center in CM01?

In OPU3 should active for capacity generation.

And check your control key for are mark for capacity?

Then in work center capacity view all work center should mark for finite scheduling?

Then run MRP with planning mode -3 and check your result and come back.