Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Routing Machine time is not considered in planned order

While taking Mrp Run , routing Machine time is not considered for semi finish goods planned order

Case

There are 4 processes to convert raw material to finish, defined 4 semi finished items and there routing with Machine Process time, following parameters are mention for each semi finish item

u2022 Routing has base quantity of 1 EA and machine time as 120 Min.

u2022 Schedule margin key = 000 i.e all the float values is zero

u2022 In-house processing time in material master is 1 day

All 4 item planned order start date and finished date is the same.

Pls. guide.

Prakash

Former Member
Not what you were looking for? View more on this topic or Ask a question