on 09-22-2008 3:10 PM
While taking Mrp Run , routing Machine time is not considered for semi finish goods planned order
Case
There are 4 processes to convert raw material to finish, defined 4 semi finished items and there routing with Machine Process time, following parameters are mention for each semi finish item
u2022 Routing has base quantity of 1 EA and machine time as 120 Min.
u2022 Schedule margin key = 000 i.e all the float values is zero
u2022 In-house processing time in material master is 1 day
All 4 item planned order start date and finished date is the same.
Pls. guide.
Prakash
Dear Prakash,
While running MRP what MRP control parameters are you using?
Check whether are you using value 2 for scheduling i.e Lead time scheduling and while running next time
use planning type as 3 Delete and recreate Planning data.
After taking the MRP run,now check whether are you able to see the operation start & end times.
Check & revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
what is ur expectation from the system? how it should behave?
Pravin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In MRP run select 2 (lead time schedulling) against the schedulling processing key then it will consider routing
I assume u have maintained capacity and schedulling view for the work center.
Edited by: BNR on Sep 22, 2008 4:21 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I tried with option 2 - Lead Time Scheduling and Capacity Planning, still it is not working.
In work center -> Capacity View
Capacity Category : 001 u2013 Machine
Processing Formula : SAP006 - Prod.: Machine rqmts
Control CapacityReduction : Formula-Related (in all three combo)
In work center -> Scheduling View
Capacity Category : 001 u2013 Machine
Processing Formula : SAP002 - Prod.: Machine time
Above parameter are maintained, if something is missing pls. guide.
Prakash
Hi,
Please check the capacity of work center in CM01?
In OPU3 should active for capacity generation.
And check your control key for are mark for capacity?
Then in work center capacity view all work center should mark for finite scheduling?
Then run MRP with planning mode -3 and check your result and come back.
Regards,
R.Brahmankar
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.