on 09-22-2008 2:51 PM
Hallo,
I would need clarification on MM SUS scenario for Schedule Agreement.
Once Schedule Agreement is released in MM, is sent to SUS.
Now what can be done in SUS?
is supplier sending Response and then the Shipping Notification?
In sending the response, the supplier can reject and modify like in MM SUS Purchase Order scenario?
can write comment for each line?
regards,
marco
is supplier sending Response and then the Shipping Notification?
After releasing of Scheduling Agreement, buyer will release Delivery Schedule (SAR - Schedule Agreement Release)
for that supplier should do Confirmation.
No need of ASN ( Advance shipping notofication) for Scheduling Agreement.
In sending the response, the supplier can reject and modify like in MM SUS Purchase Order scenario?
yes he can reject and modify based on the role authorization maintenace.
can write comment for each line?
Yes he can write comment ( for example rejection reason)
Hope it helps
Thanks
Giri