on 09-22-2008 2:46 PM
Can any one tell me is it possible to have Third party service orders(which creates PR and inturn PO on MM side).
If it is possible plese send us the configuration requirement.
Regards,
Babs.
Thanx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
3rd party sales is controlled by item catg TAS. for ehich schedule line catg is CS. Settings for CS in VOV6 will make it possible to create a pruchase requisition NB. PR to PO conversion settings is done by MM.
So when the PO is created delivery NL is fulfilled. When the goods arrive at your plant a GR is done which will post the stock & increase the plant inventory. From there you fulfill the normal LF delivery.
Pls refer http://help.sap.com/erp2005_ehp_03/helpdata/EN/70/a7853478616434e10000009b38f83b/frameset.htm
for further info
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.