on 09-22-2008 2:35 PM
Dear Friends,
Plz explain, the below strategies briefly,
MTS:
10 - Make to Stock
40 - Planning with final assembly
70 - Planning at assembly level
Here what is is the exact difference between 10, 40 & 70 some thing specific............
MTO:
20 - Make to order
50 - Planning without final assembly
60 - planning with planning material
82 - Assembly processing
Here what is the exact difference between 20, 50, 60 & 82 something specific............
Thanks in advance.
Arun.
MTS:
10 - Make to Stock : System will create plan order after considering the stock
40 - Planning with final assembly, System will create plan order after considering the stock and PIR for final assembly
70 - Planning at assembly level, System will create plan order after considering the stock and PIR for assembly
MTO:
20 - Make to order, System will create order specific plan order and not consider the free stock, PIR
50 - Planning without final assembly, System will create plan order but can not be converted to production order unless there is a sales order
60 - planning with planning material, U can plan with some other material, system will consume the stock of that
82 - Assembly processing, As soon as a sales order is created system will create a production order
Hope it is clear
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.