Plz explain, the below strategies briefly,

MTS:

10 - Make to Stock

40 - Planning with final assembly

70 - Planning at assembly level

Here what is is the exact difference between 10, 40 & 70 some thing specific............

MTO:

20 - Make to order

50 - Planning without final assembly

60 - planning with planning material

82 - Assembly processing

Here what is the exact difference between 20, 50, 60 & 82 something specific............

Thanks in advance.

Arun.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

MTS:

10 - Make to Stock : System will create plan order after considering the stock

40 - Planning with final assembly, System will create plan order after considering the stock and PIR for final assembly

70 - Planning at assembly level, System will create plan order after considering the stock and PIR for assembly

MTO:

20 - Make to order, System will create order specific plan order and not consider the free stock, PIR

50 - Planning without final assembly, System will create plan order but can not be converted to production order unless there is a sales order

60 - planning with planning material, U can plan with some other material, system will consume the stock of that

82 - Assembly processing, As soon as a sales order is created system will create a production order