Former Member
0 Kudos

How should i configurate in the IMG-project system-material-Procurement indicator for material components

,and Check acct asst categories and document types for purc.reqs,also network profile, so that i can get purc.reqs and reservation at the same time when adding a material to the activity below a wbs?

Right now it just has reservation no purc.reqs.

Thanks!

regards,

tiger wu

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi,

Please check in material master of the material. In MRP 4 tab in Individual/coll. box, check the entry whether it is 1 or 2. If it is 2 then while attaching the material system will not ask you any option and will directly take procurement type as 'Reservation for network'

If it is 1 then it will ask the option which you desire.

Regards

Former Member
0 Kudos

Dear,

Maintain procurment indicator by OPS8,Material Flow in Network,NF. for network.

Then try.

former_member214674
Contributor
0 Kudos

Hi Check network profile in OPUU..."Res/Purc.req" should not be 1...make it 2 and try.

Regards