Counter based Maintenance Plan

Former Member
0 Kudos

I want to execute a Preventive Maintenance Plan for Diesel Generator of 250 hrs, 750 hrs, 1500 hrs, 3000 hrs, 5000 hrs, 10,000 hrs.

I want to create a Maintenance Strategy or Cycle Set.

If I need to create a Maintenance Strategy how can i create a scheduling indicator for performance based. For the sap standard system i want to select scheduling indicator as Activity.

Guide me how to process.

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

for strategy based maintenance plan kindly create maintenance strategy using IP11 in what while creating there is option to specify the activity then assign this strategy to the task list and create on strategy based maintenance plan

regards

thyagarajan

Answers (1)

Answers (1)

Former Member
0 Kudos

HI

you need to create maintenance strategy gor the hour base maintenance.

hourly packages ha to maintain

like 1.250hrs,2.750hrs,3.1500 hrs etc.

-ashok