Hi friends,

Is there any difference between creation of BOM,Routing,production order for configurated material and other materials. if yes kindly guide for this.

Regards,

Renu...

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Routing is nothing but your Process Plan

Explain the step how to create routing?

By : Vishal Patil

You have to proceeds following steps:

1) CA01 - Create routing

First screen = Material on which you have to create a routing

Plant

Second screen = Usage 1 if you create routing for production purpose.

Status 4 release general

Enter

2) Now go on to application tool bar and select operation

Here you have to enter work center, control key and description

For eg. w/c 1 plant pp01 description

w/c 2 plant pp01 description

plant pp99 goods reciepts

3) Now select the component allocation

Select the material here and click on to the new assignemnt for assign the operation seqence on to the material.

4) SAVE

Now routing is create with routing group number .

BOM - Bill of material

How to Create a Simple BOM?

Transaction code : CS01

Material : Your Material code

Plant : Your Plant

BOM Usage : 1

Item Category Componment Quantity

0010 L Your Material code Your required quantity

Save your entries

You can used CS02 to changed the BOM and CS03 to display the BOM.