Hi experts,
During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.
MRP type = V1 (Reorder point planning)
Lot size = HB
planned delivery time = 0 days
What could be the reason for it? Pls help me out.
Thanks in advance,
Rgds,
jay
Hi
check reschedulling horizon in OPPQ if it is a plant, or check OPPR if u r maintaining MRP groups. Increase the days to 999, and run MRP.
Pls revert back
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When u keep your planning horizon 100 and in MD02 if ur using NETCH planning then system will consider the planning in between 100 days only If your open PO in out of planning horizon then it will not consider for the same.
If u want to do the same u have to go for increase ur planning horizon time in OPPQ.
whatever u required.
Kind Regards,
Nilesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In tcode OPPQ define plant parameter, select rescheduling horizon. It is given 100 days. Change to 200 day , now system will consider open PO.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.