MRP run problem

Hi experts,

During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.

MRP type = V1 (Reorder point planning)

Lot size = HB

planned delivery time = 0 days

What could be the reason for it? Pls help me out.

Thanks in advance,

Rgds,

jay

Former Member
Former Member replied

Hi

check reschedulling horizon in OPPQ if it is a plant, or check OPPR if u r maintaining MRP groups. Increase the days to 999, and run MRP.

Pls revert back