MRP run problem

Hi experts,

During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.

MRP type = V1 (Reorder point planning)

Lot size = HB

planned delivery time = 0 days

What could be the reason for it? Pls help me out.

Thanks in advance,

Rgds,

jay

replied

Hi

check reschedulling horizon in OPPQ if it is a plant, or check OPPR if u r maintaining MRP groups. Increase the days to 999, and run MRP.

Pls revert back