cancel
Showing results for 
Search instead for 
Did you mean: 

MRP run problem

former_member506481
Participant
0 Kudos

Hi experts,

During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.

MRP type = V1 (Reorder point planning)

Lot size = HB

planned delivery time = 0 days

What could be the reason for it? Pls help me out.

Thanks in advance,

Rgds,

jay

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

check reschedulling horizon in OPPQ if it is a plant, or check OPPR if u r maintaining MRP groups. Increase the days to 999, and run MRP.

Pls revert back

Answers (2)

Answers (2)

Former Member
0 Kudos

When u keep your planning horizon 100 and in MD02 if ur using NETCH planning then system will consider the planning in between 100 days only If your open PO in out of planning horizon then it will not consider for the same.

If u want to do the same u have to go for increase ur planning horizon time in OPPQ.

whatever u required.

Kind Regards,

Nilesh

Former Member
0 Kudos

Hi,

In tcode OPPQ define plant parameter, select rescheduling horizon. It is given 100 days. Change to 200 day , now system will consider open PO.

Regards,

Dharma