Hi experts,

During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.

What could be the reason for it? Pls help me out.

Thanks in advance,

Rgds,

jay

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

The Planning Horizon entry for your plant must be 110 or more. Check it out in OMI8. Click on the 'Maintain' button after entering ur plant, click on 'Planning Horizon' to see the entry.

For open PO qty to be considered, try running MRP run with processing key as 'NETCH' in MD02 or whichever t-code u use this doesn't take planning horizon into account.

Amit G

kunal_ingale
Active Contributor
0 Kudos

hi

check ur plannaed del time in mrp view inmaterial master

regards

kunal

former_member506481
Participant
0 Kudos

thanks for the reply

planned delivery time in Material Master = 0 days

regds

jay

former_member506481
Participant
0 Kudos

hi experts,

pls reply to my query

rgds

jay