During MRP run for a material , open PO quantity is not considered If delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.
What could be the reason for it? Pls help me out.
Thanks in advance,
Rgds,
jay
The Planning Horizon entry for your plant must be 110 or more. Check it out in OMI8. Click on the 'Maintain' button after entering ur plant, click on 'Planning Horizon' to see the entry.
For open PO qty to be considered, try running MRP run with processing key as 'NETCH' in MD02 or whichever t-code u use this doesn't take planning horizon into account.
Amit G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check ur plannaed del time in mrp view inmaterial master
regards
kunal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi experts,
pls reply to my query
rgds
jay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.