Resource capacity profile extension

Former Member
0 Kudos

Hi Experts

I want to put the resource utilisation in Capacity profile(Resource master data).

In my capacity profile, it is showing upto Mar,2009 and i want to do the planning from April, 2009 to Mar, 2010. Please tell me how to extend my capcity profile upto mar, 2010.

Regards

Guru

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

You need to change planning paramet in Genral Tab of resourse master . You can maintain the period using the range -days to +days