Hi PM Experts,

I Have created a multiple counter plan with link OR.andcycle set having cycle

5 Hour (Annual estimate 3650 h )

( Activity per day 10 h )

6 Meter quieb/hour. (Annual estimate 3650 m3/h )

( Activity per day 10 m3/h )

i have created two measuring point with hour and m3h characterstic for same equipment.What my problem is while entering measuring document even the counter reading is not reached up to the cycle any of them as given above.After scheduling the system is generating call object.As per me the system should generate call object when any one of the counter reading should reach either or equal to the cycle then system should generate the call object not before that.

Please put your valuable suggestion to overcome this problem

Regards,

RC

replied

hi

The planned date for which a maintenance order is created depends on the operation type in the multiple counter plan. In the case of an OR operation, the system selects the earliest planned date. In the case of an AND operation, the system will select the latest

also refer [Scheduling|http://help.sap.com/saphelp_46c/helpdata/en/3c/abb350413911d1893d0000e8323c4f/content.htm]

regards

thyagarajan