issues in sub-contracting

Former Member
0 Kudos

in subcontarcting scenario i have one issue

issue 1:

Materials (both excisable and non excisable) are supplied to

subcontracting vendor.

At this time in 57Fc challan only excisable items are maintained.

But in sap while creating the sub contracting challan it is showing all

excisable items and non-excisable items.

But as per client requirement non-excisable items only should be displayed

while creating /reconciling/completing the sub contracting challan.

issue 2:

when semi finished material is returned back to client by sub contractor

some raw material is still with the vendor.

while raising sub contracting order to the vendor against the same

material ,system should pop up how much raw material left with that

subcontracting vendor .

Kindly give me solution for this scenario.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

All the materials which are declared for excise have to be maintained against the respective chapter ID's. Please refer the settings in excise rate maintenance.i.e j1id.

If only the non excisable items have to be appeared then only maintain the same.

Please check if it helps. As I suppose you will get the help in J1id.

Regarding issue 2:

Is it the scrap that is produced at the the subcontractors level or the main parent raw material which is left??

If scrap is left then that has to be mentioned along with the components provided at the sub contractors level.

If the parent material is left then it has to be checked at the stocks at the subcontractor level and brought back by GR against 101 mvt type.

The BOM has to be defined accordingly. If semi finish of 1 is to be produced by supplying 2 parts of raw material then mentioned only the one which is required. Do not supply additional extra Quantity.

Regards,

Prasanna.