on 09-21-2008 8:39 PM
Dear Pals,
When ever I am creating OR, requested date of delivery is not the present date, but it is coming after two days(i.e. if I request for today, it is giving after Plus two days). I have checked at VOV8 for the proposed date, I have not mentioned any specific date. Please let me know, how to over come this.
Regards
Madhu Vaddi
Hi there,
In VOV8, in requested delivery date view, there is a field called "Lead time in days". Leave that field blank. Also check the field Propose delivery date. This will propose the current date as the delivery date.
Also confirmed delivery date is based on availability check. Basing on the MAD Material availability date, system will confirm the delivery date.
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Shivanand,
In vov8, lead time, I kept it blank and system propose date Check mark also, removed, then it is clearing delivery after 2 days. So, the settings are delivery (Availability check area). Therefore, request you to how to check, or remove this availability area delivery date.
What is the tcode to configure this.
Regards
Madhu
Hi Madhu,
plz do like :
1.VOV8 Lead time - 0 or Blank
2. propsed del date - tick
3. date type - days
4. VOV7 - Schedule line relevent
untick
5. VTLA- Document flow shud be tick at item level.
let me know ur query status
thanks
mahi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
at sale document type level
lead time in days kept it blank
thanks
bhushan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.