ATP quantity = 9.999.999.999,999 if future delivery date

Former Member
0 Kudos

Dear All,

We have enabled ATP control during sales order creation. If delivery date is set to today's date

the ATP control calculates ATP quantity well. But if the delivery date is set to future date

system says that 9.999.999.999,999 pieces of material is available.

Why this happens?

Best regards,

Mark

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check Inhouse production time in material master. This field should have a value.

Regards,

GSL.