Purchase order not appearing as commitment for next fiscal year in KOB2

Hi Experts

Any help on this is highly appreciated.Our Fiscal year 2008 is ending on 27th september and fiscal year 2009 will start on 28th September.

We have some purchase orders created with delivery date as 30th september which falls into next fiscal year. Somehow these purchase orders are not appearing as commitments in KOB2 report even with data ranges for next fiscal year.

However we have many similar Purchase orders with delivery date in fiscal year 2008 with same internal order as account assignment and they are correctly appearing as commitments in KOB2 report.

Can you please let us know what could be the reason for purchase orders with delivery date as 30th september not appearing in KOB2 report.

Regards,

Santosh

Former Member
Former Member replied

Dear Santosh, Yes. You run the said SAP standard program and let us see, whether it resolves our problem. Perhaps the post-extension of the validity period must be the deficiency for this problem. Trust this helps much! Cheers,