on 09-20-2008 12:15 PM
Hi,
My requirement is, I want the work-center timings to reflect in my call object (Maintenance Order) generated through a maintenance plan.
My scenario is: I've made a work-center with the following data,
wrkcntr category as 0005; usage 004; control key PM06 with scheduling indicator checked;
in capacities start-finish timings as, 06:00-14:00; operating time of 8hrs, and factory calendar is chosen for maint. people.
The order type say pm08 is selected.
now in the maint. plan we choose this work center in the planning data field.
Task-list is also attached and the data are OK.
in maint. plan scheduling parameter shift factor etc NOT given.
Now when after schedulling I got one order with the
SchedStart: DD.MM.YYYY 06:00
Sched.Fin.: NEXT DATE 06:00
but I need the date to be 06:00 to 14:00 as in the respective work-center.
For for fastly solving the problem my analysis:
I checked the order,goto operation tab,goto dates tab and found that basic finish time of activity is 24:00:00
If this is the reason than how to make it 08:00:00 default for this order type.
Thanks in advance,
hi guys closing the issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
what is the work hours specified in the operation ,also what is the break hours you have specified
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tyag,
sorry my network was not wrking.
Further the operation timing (single operation) is 7hrs only.
break hrs I hv not specified yet.
actually I hv made a simple one.
and for your info when I checked the call order
in operation tab,and clicking on dates tab found that
start time is correct as per wrkcentr but finish time of activity is after 24 hrs i.e next date and same time.
and one more thing there is restriction field and its showing 24:00:00 may be this is the reason.
kindlyhelp
If this is the reason than how to make it 08:00:00 default for this order type.
Hi Tyag,
the details are cmins as below
Erl. start: 19.09.2008 06:00:00 Earl. fin. 20.09.2008 06:00:01
LatestStart: 19.09.2008 06:00:00 LatestFin. 20.09.2008 06:00:01
Act. start: 00:00:00 Act. finish 00:00:00
FcstFinish 00:00:00
Restriction
StartPoint
End 24:00:00
I am new to this and need your help.
The req is how to reflect wrk center timing in the wrk order generated through a maintenance plan.
Regards,
sanjay
Edited by: ganesh sarasvati on Sep 23, 2008 11:47 AM
Dear,
Take lead for operation more so that you can observe changes.
Now I am doing the same but I am not facing the problem which you are.
Remember scheduling takes place after saving the order and the coming in change option you will observe.
Regards,
Kaushal Rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.