Controlling Area, Currency in Investment program

Former Member
0 Kudos

My company is having offices in 3 countries,India,Indonesia and Thiland.

In India SAP is already implemented and now i m doing roll out in Indonesia ,here the fiscal year and Currency is different(INR to IDR) .

Controlling area ,Fiscal year is also different than india,so how to take care of this problem Fiscal year variant, Controlling Area,Currency in Investment program.

or can you suggest me that investment program is being created at compny code lever or controlling area level.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

dear shahi,

go to t code im22. u ill find ur answer.

Former Member
0 Kudos

Hey Shishir,

IM22 is for the Creation of Investment programme position its okay,here u creat ur own Programme position....but my question is something different go throught it again.

Former Member
0 Kudos

Hi Shashi,

All the best for your Role out.

Currencies can be updated for both plan and actual values. The use of more than one currency must be allowed in the controlling area.

You can plan in the following currencies:

Controlling area currency

Object currency

Transaction currency

Currency of the user's choice

Please refer the link below.

[http://help.sap.com/saphelp_47x200/helpdata/en/d8/b80d38df9e9010e10000009b38f8cf/frameset.htm]

For Fiscal Change you can check refer below link for IM.

[http://help.sap.com/saphelp_erp60_sp/helpdata/en/2a/f9f294493111d182b70000e829fbfe/frameset.htm]

Regards'

Syed