on 09-19-2008 5:03 PM
Friends,
While doing planning transfer to activity planning through KSPP the issue is like this .
Plan is updated in MD61 , and then KSPP is run using a planning scenario with version in which plan is updated
KSPP has run successfully giving cost centre wise/material wise planned activities
issue is after KSPP run whne we check in KP26 -activity planning for cost centre , instead of the plan activity should get updated with the KSPP out put it is getting displayed as Activity Scheduled .
is there any other customization or some transaction is to be run to get these activity scheduled (out put of KSPP transaction) to get updated in Plan activity field of KP26
please provide inputs
regards,
madhu Kiran
Hi, You need to run KPSI-Plan Reconciliation to overwrite the Plan activity quantities with Scheduled activity quantities in KP26 after the transferring the scheduled quantities from Long Term planning to Cost Center Accounting through KSPP. Trust this helps much! Cheers,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
analysed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.