on 09-19-2008 2:40 PM
how we can invoke project and task in timehseet?
Hello monica,
Please check the assignment of cost center with the controlling area in KS01 and then cost center to activity type in KP26.
If you want the activity type in project you need to assign the activity type in Work center which u r going to use in activities.
regards,
sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Monica,
You need to do assignment of Cost center and activity type in KP26 for the fiscal year you wanted. This can resolve your query.
regards,
sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Monica,
Goto KS01 and extend the validity period of the cost center.
Regards,
sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello Monica,
In data entry profile in default values remove activity type and also in work center of the activity remove activity type to avoid the entry of activity type in Cats. However if you want the actual cost to come on the project after the confirmation u have to maintain the activity type.
regards,
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello monica,
In order to call the task automatically in CAT2 you have to first carry out the workforce planning.
There are two routs to that
First u have to assign project team in Project then go to CMP2 and assign those persons to the desired activities. After that when you go to CAT2 and enter the person you have attached to the activity u will automatically find the task along with the default values (such as controlling area, activity type,cost center etc.) as per the configuration setting done in data entry profile.
The other route is that you assign persons to the work center which u have used in the activity. Then go to cmp3. Assign the desired person to the activity. After that when you go to CAT2 and enter the person you have attached to the activity u will automatically find the task along with the default values (such as controlling area, activity type,cost center etc.) as per the configuration setting done in data entry profile.
Hope this will solve your query.
Regards,
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.