PPM run with different productivities for annual plan

Hi Experts

I want to do the annual planning with monthly bucket, The productivity(same product) from month to month is changing in the ppm across the year.

For maintaining the different productivity for different months i have to create the different PPM.

I want to do only one SNP run for one year

please suggest is there any another method for doing it.

replied

Hi Guru,

You can define variable output for validity period while creating components a PPM.For each month you can set the output quantity as per the productivity of the month and also enable the check box "Time dependant data" within same one PPM across the year.

Thukral